Valuing Finality: Interpreting Continuous Acts in Municipal Negligence Claims

Valuing Finality: Interpreting Continuous Acts in Municipal Negligence Claims

By: Bridget Irish

Edited by: Jessica DiFederico

In Huether v Sharpe, 2025 ONCA 140,[1] the Ontario Court of Appeal provided clarity on what constitutes a “continuous act or omission” for the purpose of barring a claim pursuant to the ultimate limitation period in section 15(2) of the Limitations Act (the “Act”).

Section 15(2) of the Act stipulates that the ultimate limitation period is 15 years, meaning no claim may be commenced after this period expires. However, section 15(6)(a) of the Act provides that in instances of a continuous act or omission, the 15-year period does not begin until the day on which the act or omission ceases. The correct application of section 15(6)(a) of the Act was a central issue in this case.

Background

In May 1985, a builder applied to the Township of McMurrich Monteith (the “Township”) for a building permit to build a dwelling.[2] In July 1986, The Chief Building Official (“CBO”) carried out an inspection and identified several dwelling deficiencies on the application that had to be remedied within the ensuing weeks.[3] In August 1986, there was an Order to Comply delineating the violations. At some unknown later date, a handwritten note was added to the Order stating that it was “all complied with”.[4] In 1988, a purchaser went to purchase the dwelling, and the Township clerk issued a Treasurer’s Certificate recognizing that no work was outstanding on the basis that the Order was complied with.[5]

Fast forward to October 2021, when the plaintiffs purchased the dwelling.[6] Shortly after, in February 2022, the plaintiffs commenced an action alleging that the Township acted negligently by failing to execute all requisite inspections of the dwelling, which was not in compliance with the Building Code.[7] They claimed the dwelling had a failing foundation and that unpermitted materials were used in its construction.[8]

In March 2024, the Township moved for a summary judgment motion, asserting the claim was time-barred because the alleged negligence occurred in 1988, and the claim was not brought until 2022.[9] The plaintiffs maintained that the Township had an ongoing “duty to monitor” arising from the fact that the building permit was never formally closed. They argued that this constituted a “continuous act or omission” within the meaning of section 15(6)(a) of the Act.

Summary Judgment Motion

The motion judge considered two key issues:

    1. 1. Whether the Township had a duty to continue monitoring the permit file and to conduct all necessary inspections to put it in compliance with the Building Code;[10] and

    2. 2. Whether the plaintiffs’ claim was statute barred pursuant to s. 15(2) of the Limitations Act.[11]

The judge dismissed the Township’s summary judgment motion on the basis that the Township did not close the permit file, therefore imposing an ongoing duty to monitor the permit.[12] The judge concluded that the negligence was “continuous,” which preserved the plaintiffs’ claim within the statutory period.[13]

Appeal Analysis

On appeal, the Ontario Court of Appeal determined that the motion judge misinterpreted the meaning of a “continuous act or omission,” leading to an incorrect conclusion. Furthermore, the motion judge’s finding of a duty of care to monitor the file was also flawed, as the “well-established legal framework” on a duty of care as set out in Anns v. Merton London Borough Council, [1978] A.C. 728 was not applied.[14]

Interpretation Issue

The Court noted that the ultimate limitation period was enacted to preclude litigation concerning latent defects discovered decades after the fact. Among its objectives were to avoid costs associated with prolonged record-keeping and insurance liabilities, and to address the challenges of lost evidence with the passage of time.

Subsequently, the Court of Appeal considered the exception for a “continuous act or omission” under section 15(6)(a) of the Act. It held that a continuous act or omission requires “a repetition of actionable conduct on a continuous basis.” This is not very common in tort, but examples include nuisance and trespass.[15]

The Court concluded there was no successive or repetitive conduct by the Township. The mere fact that the Township left the permit file open did not satisfy the requirement for a continuous act or omission.[16] The Court noted that even if the Township had a duty to monitor open building permits (that question discussed below), the existence of that duty alone does not amount to a continuous act or omission by the Township. Accordingly, the claim was statute barred pursuant to the Act.

Duty of Care

The Court of Appeal further held that the motion judge erred in finding a novel “duty to monitor” open building permit files without first undertaking a proper duty of care analysis. The Court did not undertake the analysis itself but identified that this duty was a novel one and required a full analysis under the Anns/Cooper test. The motion judge did not consider this two-part test in their analysis. Regardless, a further analysis of this issue became moot since the claim was ultimately statute barred.

Decision

The Court of Appeal set aside the motion judge’s order and dismissed the action against the Township.

Takeaways

This decision clarifies that under section 15 of the Act, a “continuous act or omission” does not refer to sustained exposure, but rather to repeated and recurrent actionable conduct that is continuously renewed.

Moreover, this case served as a reminder of why there is an ultimate limitation period. In this case, the construction occurred approximately 36 years before the origination of the claim which posed significant practical challenges, particularly given that the parties involved in the construction and permit were deceased, and the evidence was aged and incomplete.

The ultimate limitation period serves as a mechanism to protect municipalities from negligence claims arising from conduct that is discovered only decades later.

 

[1] Huether v. Sharpe, 2025 ONCA 140 (CanLII).

[2] Huether v. Sharpe, 2024 ONSC 1987 (CanLII) at para. 12.

[3] Ibid at para. 15.

[4] 2025 ONCA 140 at para. 9.

[5] Ibid at para. 16.

[6] Ibid at para. 17.

[7] Ibid at paras. 18.

[8] 2024 ONSC 1987 at para. 2.

[9] 2025 ONCA 140 at para. 3.

[10] Ibid at para. 20.

[11] Ibid at para. 21.

[12] Ibid at para. 22.

[13] 2024 ONSC 1987 at para. 56.

[14] 2025 ONCA 140 at para. 61.

[15] Ibid at paras. 40-41.

[16] Ibid at para. 46.

Insights & Commentary

Flexibility in Administrative Dismissals under the Class Proceedings Act - photo
  • Commentaries

Flexibility in Administrative Dismissals under the Class Proceedings Act

By Kayla Sager In Tataryn v Diamond & Diamond Lawyers LLP,[1] the Ontario Court of Appeal upheld the dismissal of a class action for delay under section 29.1 of the Class Proceeding Act which came into force on October 1, 2020. Justice Pepall, writing for the panel addressed the application of s. 29.1(1) of the … Continued

No Negligence Act, No Problem: Court of Appeal Affirms the Apportionment of Fault in Contract Cases - photo
  • Commentaries

No Negligence Act, No Problem: Court of Appeal Affirms the Apportionment of Fault in Contract Cases

By: Zachary Sherman Edited by Grant Ferguson and Thomas Russell   In Arcamm Electrical Services Ltd. v. Avison Young Real Estate Management Services LP (“Arcamm”),[1] the Ontario Court of Appeal overturned a summary judgment motion where the issue of “contributory fault” in a contract dispute remained unsettled. Justice Gillese, writing for a panel of judges, … Continued

Stolove v. Waypoint Centre for Mental Health Care: Recent Developments in Systemic Negligence in Class Actions - photo
  • Commentaries

Stolove v. Waypoint Centre for Mental Health Care: Recent Developments in Systemic Negligence in Class Actions

By Christian Breukelman and Bridget Irish On June 25, 2024, Justice Perell released his decision on a certification motion in Stolove v. Waypoint Centre for Mental Health Care, 2024 ONSC 3639. This decision has significant takeaways for the growing number of potential class actions rooted in ‘systemic negligence.’ Stieber Berlach LLP represented Waypoint Centre for … Continued

by

No Reporting, No Relief Under Claims Made and Reported Policies - photo
  • Commentaries

No Reporting, No Relief Under Claims Made and Reported Policies

By Zachary Sherman In Kestenberg Siegal Lipkus LLP v Royal & Sun Alliance Insurance Co of Canada, the Ontario Court of Appeal confirmed that relief from forfeiture is unavailable to insureds who fail to report a claim to their insurer under a “claims made and reported” policy. The decision also affirms that the language requiring … Continued

All News